We have a cluster with 100 workers in our lab, and I am allowed to use up to 40 workers. The problem is that I cannot submit more than 40 jobs at once, because those extra jobs will use the idle workers of my colleagues. How can I tell MATLAB job scheduler to limit my access to only 40 workers? I don’t think the solution is setting “NumWorkersRange” to [1 40].
0 commentaires
Réponse acceptée
Edric Ellis
le 30 Avr 2015
If you're using an MJS cluster, then NumWorkersRange on a single independent job is the way to do this. You'll need multiple createTask calls, a bit like this:
c = parcluster(...);
j = createJob(c, 'NumWorkersRange', [1 40]);
for idx = 1:N
createTask(j, @myFcn, numOutputArgs, {inputArgs, ...});
end
submit(j);
Plus de réponses (0)
Voir également
Catégories
En savoir plus sur MATLAB Parallel Server dans Help Center et File Exchange
Community Treasure Hunt
Find the treasures in MATLAB Central and discover how the community can help you!
Start Hunting!