Hello, I want to trigger a subsystem that will then run for 0.25 time units (more than once) at points through the simulation but I do not know how to trigger a clock. Can anyone help?
Roger

Réponse acceptée

Roger
Roger le 20 Juin 2011
The solution to this problem can be solved using 'Reset clock' block written by Ravi Mravi which is very elegent and can be built out of standard blocks. This would be a clock that would be running from the start but could be set to zero at any point by a trigger. see: http://www.mathworks.com/matlabcentral/fileexchange/5761

Plus de réponses (2)

Fangjun Jiang
Fangjun Jiang le 24 Mai 2011
I am not fully understand your question. Let's see if this is the case. Set your simulation step size as 0.01 second. Drag a "Pulse Generator" block, set the period as 1 second and the pulse width as 25 (percent). Use the output of the "Pulse Generator" to trig an "Enabled Subsystem". The subsystem will be running every 0.25 second out of 1 second.
  1 commentaire
Roger
Roger le 25 Mai 2011
Thank you for taking the time to consider my problem. As Mark said in his reply I am not sure of the time between triggers - but this was not clarified.

Connectez-vous pour commenter.


MarkB
MarkB le 24 Mai 2011
Fangjun's approach is probably the best way if the interval between the 0.25 pulses is also known in advance. If it is not, I would recommend using Stateflow instead.
The general idea is that you would still use an "Enabled Subsystem" like above, but in this case, Stateflow would output a Boolean signal to drive it. Inside Stateflow, you could read any relevant inputs, and use them to enter a state that sets the output as "true", only exits after 0.25 (check the documentation for "temporal logic" to see the Stateflow keywords for defining time intervals), and then sets the output to "false" upon exiting the state.
  5 commentaires
Roger
Roger le 26 Mai 2011
The trigger is another process exceeding a maximum value. So every time the other process results in a parameter getting larger than say 10, I need a process to be triggered to run for 0.25 time units.
Sorry about not replying earlier did not realise that I did not get notified about comments. In the mean time I think I have found a work around.
My solution:
The actual value I need to produce (and hold) from my subsystem is zero so I made a circuit where:
- the value from the external system is feed into a "compare to constant" block (if above set value then has value of 1)
- this feeds into a "zero order hold" block with time span set to 0.25
- this feeds into "matlab function" block (u) along with another feed which gives standard feed (Q) as long with following code:
function Q_final = fcn(u,Q)
%#codegen
if u > 0
Q_final = 0;
else
Q_final = Q
end
- Output is what I want.
This is a pig ugly way of achieving goal and if anyone else has a simpler way of holding values or triggering systems for set amount of time I am still interested.
Fangjun Jiang
Fangjun Jiang le 26 Mai 2011
The use of Matlab function block is not needed. You could just use a switch block.

Connectez-vous pour commenter.

Catégories

En savoir plus sur Schedule Model Components dans Help Center et File Exchange

Tags

Produits

Community Treasure Hunt

Find the treasures in MATLAB Central and discover how the community can help you!

Start Hunting!

Translated by